May 26, 2016
Royal Carribbean Cruises
Grand Bahama shipyard, BAHAMAS
Duration: December 2013 – February 2014 (4 weeks drydock duration)
Manpower: 51 workers + on site management team.
Scope of Work: Major refurbishment during the dry-dock on Deck 12. Pre-Outfitting of new blocks on the ground. Full outfitting of new cabin area that included 38 cabins plus corridors. + on site management team.